How to get Building Permit In Ghana

How to get Building Permit In Ghana

Requirements For Building Permit In Ghana

What Is A Building Permit?

A building permit is described as “a written permission authorizing a person or company to carry out development in accordance with the conditions specified in the permit” by the Metropolitan of Ghana. Such development permits must take into account the proposed development’s structural requirements, planning standards, and zoning restrictions. The importance of a building permit is due to the fact that effective planning and management of community development increases orderliness, convenience, public safety, and economic development.

A building permit is an authorized document issued by the local government to an individual, company or corporation to commerce either a new structure or an existing one that needs expansion. It is important to note that even demolishing a structure also requires the owner to obtain a permit.

How Much Does A Building Permit Cost?

Fees must be paid at every step of the building permit application process. These fees may vary depending on the municipality. Below are some of the building permit costs in Accra:

  • Building permit form – GHS 100
  • Submission and processing of documents – GHS 50
  • Site inspection – GHS 100

Requirements For Issuing A Building Permit In Ghana.

  1. Submission of building permit application form to the Statutory Planning Committee.
  2. Submission of a land ownership document obtained from the lands commission.
  3. Attachment of four (4) copies of Architecture drawings which should be signed by a certified Architect.
  4. Attachment of four (4) copies of Structural drawings also signed by an engineer.
  5. The presented details on the application form must agree with the mode of the project to be embarked on.
  6. A soil test report must be presented which is supposed to be certified.
  7. A fire-certified report must be obtained from the Ghana Fire Service which should also contain drawings from the report.
  8. A permit must be produced which should be obtained from the Environmental Protection Agency, that is (EPA).
  9. In the case where the building or the structure has commerce already or even completed, it will be required to provide a structural integrity report

How To Apply For A Building Permit In Ghana

The following are the procedures you need to follow to acquire a building permit from the local government;

1. Submission of application to the secretariat of Statutory.

Send the SPC the documents mentioned in the paragraph above. The SPC will examine your submission for compliance and give you technical advice regarding your application. They will review your documents and make any suggested changes or amendments after. After you pay a fee, your record will be added to the database.

2. Vetting

The next step is vetting after the Review and any necessary changes have been made. There are three levels of vetting that need to be finished before a building permit can be issued. vetting by the Physical Planning Department, the Works Department, and other pertinent organizations depending on the type of structure you are building

Inspection by the Works Department: The works department inspects the building’s structural integrity and architectural elements.

zoning reviews, planning assessments, and consultations will be carried out as needed by the physical planning department.

Examination by Other Relevant Agencies: Depending on the type of building, other relevant government organizations may conduct technical evaluations prior to approving your construction.

3. Collating Technical Findings

As soon as the screening procedure is finished, the secretariat will make the technical findings available for collation and arrange a site inspection.

4. Site Inspection

Advertisements

To make sure the paperwork corresponds with the project, a work engineer and a physical planner visit the applicant’s application site.

5. Technical Consideration Of The Application By The Technical Sub-Committee.

An evaluation and any necessary recommendations are made to the SPC as a result of the inspection.

6. Consideration Of Application

In this case, the SPC will evaluate and consider the entire application. If all requirements are met, the application will be approved, refused, or deferred for further consideration.

7. Processing of Statutory Planning Committee’s decision

A decision is then issued by the SPC to the applicant. Building permit certificates are prepared and endorsed by both the SPC and the works engineer for the applicant if approved. At this point, all fees must be paid.

8. Development Permit Issuance

At this stage, the applicant will know whether the building has been approved or rejected. If approved, the applicant receives a building permit in Ghana.

In a case where the application was rejected after the entire process for one reason or the other. SPC will provide you with feedback regarding why your application was rejected. The SPC will discuss queries and appeals with you.

9. Appealing And Resubmission Of Application

The SPC’s conclusions are still subject to appeal and revision. If your application for a permit is denied and you still want to move forward with the construction, you must appeal to the Regional Coordinating Council. When you get their response, you can reapply using an updated form.

This comprehensive guide will help you obtain a building permit in Ghana. Getting a building permit might not be simple, but if you follow the above instructions, it shouldn’t be too challenging.

Advertisements

Leave a Reply